Meehan’s progress 11-12-18

Sorry for the delay in posting. Here is a brief description of what has been done over the past month.

All electric has been run

A new sidewalk has been installed

All cable, fire and security systems have been installed

Most of the drywall has had a first coat of mud.

Kitchen walls are completed and tile is going in now.

All the Stone work in the front is done

Items they are working on now:

Installation of the cooking hood, next week with equipment to follow shortly there after

Ceilings in the entrance, bar area and upper level dining

Tile in the locker room area

Sinks counter tops in the locker room.

And much more to come. Stay tuned.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s